Issues to be noted during the installation of gantry cranes

Issues to be noted during the installation of gantry cranes

info-596-417

1. Most of the main beams of gantry cranes are transported to the site in sections. On site docking and assembly. After assembly and welding, check several dimensions. It was found that there is a difference between the mid span camber and cantilever uplift, and the values of mid span camber and cantilever uplift need to be adjusted immediately.
2. The components of the gantry crane are too long and cannot enter the site due to travel issues, which is a common occurrence. The first priority is to make a good luck delivery plan and fully consider the emergency measures for the presentation of this phenomenon. The common method is to prepare a sedan crane in advance. Traverse with the transport convoy. Once it becomes difficult for a car train to turn, use a car crane to lift the combination of the crane's super long components and trailer, and coordinate with the tractor for turning.
3. The main beam of the crane was found during the trial lifting. The lifting capacity in practice is greater than the value planned for the device. This phenomenon has been observed at the installation site. The general reason is that the budget component presents a negative error; According to the on-site practice, the lifting load has been increased. When formulating the installation plan, it is necessary to fully consider this phenomenon. So when placing the crane, its orientation should have a high safety factor.
4. After the completion of the gantry crane device, it was found that the viewpoint of the flange connecting the support legs and the trolley beam was incorrect. It is necessary to make adjustments. The various supports or cable wind ropes of the support legs shall not be removed, and the joint weld between the flange and the support legs shall be cut open. Adjust the viewpoint before welding.